A QUICK GUIDE TO THE PRODUCTION PROCESS:

  1. Prepare Tech Packs for your designs. (Use our designer if you don’t have Them.)

  2. Pull and Select Desired Fabrics and Trims.

  3. Create a Time and Action Calendar which calls out Milestone Dates in the production process.

  4. Order Sample Fabric and Trims.

  5. Factory Creates the Pattern.

  6. Factory makes the Sample. This should also be for Fit.

  7. Fit the garment (can take 1-3 Fit sessions)

  8. Order the Bulk Fabric, Trims, Labels and Tags.

  9. Factory Creates the Mark and Grade

  10. When all Raw materials are in Factory, Pre Production begins

  11. May receive a Pre Production Sample - this is a reference for Bulk Production

  12. Proceed with Bulk Production - 4-8 Weeks.

  13. Run QC Checks - In line, At finishing table and if Client wishes, a third party Inspection. (SGS or QIMA)

  14. Steam, press, Pack and Box for Shipment.

Process & Estimate of Lead Times

Fabric Development

As we look World Wide with some favorites in USA, Italy, Spain, Japan, France this can take at least 45 Days.

Sample Fabric

Takes 10 Days to arrive in Factory if stocked.

Denim Wash & Finish

Can take 14 - 30 Days each round of submits

Bulk Fabric

Can take 10 Days if Stocked, not printed.